英语翻译The cell floor and its composite liner system was sloped at a minimum of 2 percent toward the sump to promote leachate flow.The composite bottom liner system - on the 1 vertical-- to-2.5 horizontal,i.e.40 percent - side slopes was similar
来源:学生作业帮助网 编辑:六六作业网 时间:2024/12/24 21:50:30
英语翻译The cell floor and its composite liner system was sloped at a minimum of 2 percent toward the sump to promote leachate flow.The composite bottom liner system - on the 1 vertical-- to-2.5 horizontal,i.e.40 percent - side slopes was similar
英语翻译
The cell floor and its composite liner system was sloped at a minimum of 2 percent toward the sump to promote leachate flow.The composite bottom liner system - on the 1 vertical-- to-2.5 horizontal,i.e.40 percent - side slopes was similar,except the geonet was heat-bonded to two geotextiles.The composite liner system was located under the low-permeability cell berm separating the two cells.
A smooth 60-mil-thick HDPE geomembrane,underlaid by the CCL,was placed under the cell separation berm.This berm consisted of compacted clayey soils.The slopes of the cell separation berm were 1 vertical-to-2 horizontal and rose 6 feet above the geomembrane.The bean's crest width was a minimum of 15 feet.
To limit leachate migration through the cell separation berm during the lateral expansion's construction,a geomembrane flap was installed.This smooth 60-mil-thick HDPE geomembrane flap was extrusion-welded to the smooth HDPE geomembrane of the permanent liner system,which lay underneath the cell separation berm.The geomembrane flap extended 4 feet up the 1 vertical-to-2 horizontal side slope of the cell separation berm that faced the active placement area (Cell 2).
The geomembrane was anchored at 4 feet up the inside slope of the separation berm.Therefore,it did not cover the upper 2 feet of the separation berm facing Cell 2 and the cell separation berm side slope facing the lateral expansion (Cell 1).
The southern edge of the cell separation berm was located approximately 30 feet north of the extent of waste in Cell 2.The smooth geomembrane for the permanent liner system extended underneath the cell separation berm to within 1 foot to 2 feet of the bean's northern edge.To join or tie the geomembranes from Cell 2 and Cell 1 together,the northern 1 foot to 2 feet of the cell separation berm had to be excavated to expose the existing Cell 2 geomembranes prior to welding to the new Cell 1 geomembrane.
At the Cell's Intersection
To control the continual leachate outbreaks that occurred along the waste slopes' toe,soil fill was placed on the 1 vertical-to-3 horizontal waste slope.Initially,a 2-foot thick soil lift was placed over the slope toe but was unsuccessful in controlling the outbreaks.Several subsequent 2-foot thick soil lifts were also placed in unsuccessful attempts to control the outbreaks.Finally,an approximately 10-foot thick soil lift was placed over the slope and toe.The soil fill then extended into Cell 1 - the distance shown by the line at approximately a 1 vertical-to-2 horizontal slope.
It was assumed the outbreak's abundance and magnitude resulted from leachate recirculation,surface water infiltration and the lowest portion of the cell being along the toe of the interim waste slope.Additionally,the permanent sump was located at the northeastern end of the cell separation berm.It was concluded that leachate was building up behind the low-permeability cell separation berm causing the outbreaks.
英语翻译The cell floor and its composite liner system was sloped at a minimum of 2 percent toward the sump to promote leachate flow.The composite bottom liner system - on the 1 vertical-- to-2.5 horizontal,i.e.40 percent - side slopes was similar
在单元格地板及复合衬板系统是倾斜的在对促进渗滤污水流量底壳 2%的最低水平.复合底衬板系统-1 垂直--以 2.5 水平,即 40%-边坡差不多大小写敏感的只是在 geonet 的热粘到两个土工布.复合衬板系统位于下分开两个单元格的单元格低渗天然.土工一顺利 60 米尔厚 HDPE 膜,由覆铜板,underlaid 被放在细胞分离天然.此天然包括压实粘性土.细胞分离天然斜坡,一时垂直--2 水平上升 6 英尺以上,土工膜.豆的顶宽度是最少 15 英尺.若要限于横向扩展的施工过程中通过细胞分离天然渗滤污水迁移安装了土工膜瓣.这种顺利 60 米尔厚 HDPE 土工膜瓣是要躺在下细胞分离天然的永久套系统的平滑 HDPE 土工膜挤出焊接.土工膜瓣扩展了一时的垂直--2 水平边坡面对活动安排就业方面 (电池 2) 的细胞分离天然的 4 英尺.在土工膜停泊在了里面的 4 英尺的分离天然斜坡.因此,它并不包括电池 2 和面对横向扩展 (电池 1) 细胞分离天然边坡的分离天然的上部 2 脚.南部边缘的细胞分离天然是废的位于约 30 英尺以北电池 2 中的严重程度.下内一只脚 2 站起来的豆的北缘,细胞分离天然扩展的永久衬板系统顺利土工膜.加入或联系起来的电池 2 和细胞 1 geomembranes,2 站起来的细胞分离天然北部的一只脚已公开现有的电池 2 geomembranes,在向新的细胞 1 土工膜焊接前被挖出.要控制以及废物斜坡的脚趾发生的持续垃圾渗滤液暴发的单元格的交叉口,在土填放 1 垂直--3 水平废物斜坡上.最初,2 呎厚土搭车被放置在坡脚,但没有成功地控制暴发.几个后续 2 呎厚土升降机亦被放在不成功的尝试,以控制暴发.最后,一个大约 10 英尺厚土升降机放在该斜坡及脚趾.土填充,然后扩展到细胞 1-距离约 1 垂直--2 水平斜坡在行所示.假定它是暴发的数量和大小产生渗滤液循环、 水渗透和被临时废物边坡底沿该单元格的最低部分的.此外,永久的集污槽被细胞分离天然东北结束时发现.它被最后的渗滤污水建立后引起暴发的低渗细胞分离天然